The off-shore wind farm (OWF) export cable circuits up to 275 kV are characterized by:
Due to circuits lengths up to 100 km high capacitance, which requires extremely high-power demand for conventional AC test systems
Due to very long factory lengths large number of (factory) joints are installed.
There is a need to test the complete cable drum in the factory before shipping and on-site after installation
Accessibility and space constraints regarding off-shore access to the cable
No possibility for distributed partial discharge measurements on individual joints of a subsea cable
In the case of HVAC or HVDC cables, any possible defects due to installation and transportation can only be detected and located with damped AC voltage testing including partial discharge detection
Based on the damped AC (DAC) technology Onsite HV provides a variety of onsite testing solutions for the above-mentioned applications, see the data sheets.